ISLAMABAD: Engro Fertilizer has invested approximately $50 million in plant turnaround to improve reliability and operational efficiency, and the company has successfully completed the largest scheduled overhaul of its EnVen plant on June 18, 2024, with a schedule of 55 days.
Established in 2011 with an investment of $1.1 billion, the EnVen plant has an annual production capacity of 1.3 million tons and is the most energy efficient fertilizer plant.
This project includes more than 5,000 maintenance activities, including the initial replacement of the waste heat boiler, overhaul of the convection furnace section, ammonia storage tank inspection and overhaul of six main turbo trains and gas turbines.
At its peak, over 6,000 people worked day and night on the Factory floor for this conversion job.
Ali Rathore, CEO, Engro Fertilizers said: “Despite extreme weather conditions, the safe and successful completion of this major turnaround demonstrates Engro Fertilizers Group’s engineering excellence in executing large-scale projects on schedule and within budget. The safety of all involved in the activity. Critical projects this is carried out in house by our talented engineers using innovative techniques and the best safety and quality practices in the world.”
Pakistan’s food security. We thank our employees, contractors, technical partners global, local governments and other key stakeholders for their support and encouragement that contributed to the success of this important turnaround.”